An agile team is planning the next iteration for a product release that has accumulated technical debt.

What should the team do?
A . Add code cleanup activities to the product backlog and request prioritization by the product owner
B . Add code cleanup activities to the next iteration and request clarification from the product owner
C . Add code cleanup activities to the next iteration and ask the product owner to end the current iteration
D . Add code cleanup activities to the next release backlog and request documentation from the product owner

Answer: B