Posted by: Pdfprep Category: PMI-ACP Tags: PMI-ACP exam questions, PMI-ACP practice exam, PMI Certification Post Date: November 12, 2020 Pdfprep2020-11-12T13:14:27+00:00 The process of reviewing, testing, and accepting implemented features is called:A . Retrospective.B . Stakeholder review.C . Scope verification.D . Iteration planning. View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.