How should an agile practitioner work with the team to help identify the iteration’s remaining scope?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered.

How should an agile practitioner work with the team to help identify the iteration’s remaining scope?
A . Convince the team to stop planning and keep the size small
B . Identify the technically minimal and achievable tasks
C . Refer to the remaining prioritized backlog items
D . Select some of the smallest items from the backlog

Answer: C