How should the agile practitioner address this concern?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents.

How should the agile practitioner address this concern?
A . Educate the QA manager that in agile, quality is integrated from the beginning to end of the project
B . Write backlog items that include QA as part of the description
C . Ask for the current QA documents and incorporate them into the technical debt backlog
D . Ask the product owner to write tests and QA controls into the acceptance criteria

Answer: C