A project team identifies a number of technical challenges with features in the next sprint.

What should they do?
A . Request direction from the technical manager
B . Encourage the product owner to reallocate the features to another sprint
C . Determine who is best qualified to address the challenges
D . Ask the product owner to assign the tasks to the most appropriately skilled resources

Answer: D