What should the product owner do next?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.

What should the product owner do next?
A . Obtain approval from the change control board to discontinue the component
B . Ask the team to continue developing the component
C . Ask the team to discontinue developing the component
D . Request the sponsor’s formal approval to discontinue the component

Answer: D