Posted by: Pdfprep Category: PMI-ACP Tags: PMI-ACP exam questions, PMI-ACP practice exam, PMI Certification Post Date: January 3, 2021 Pdfprep2021-01-03T23:15:08+00:00 Estimating costs for an Agile project starts with which of the following types of meetings?A . Project RetrospectiveB . Steering CommitteeC . Release PlanningD . Sprint Planning View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.