For a critical project, a new team has been formed from various departments.

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

For a critical project, a new team has been formed from various departments.

The project manager should start team building by:
A . Creating a project charter, documenting roles and responsibilities of each member, and sending it to the team members.
B . Taking the team offsite for icebreaker sessions and other activities to ensure team members get to know each other.
C . Assembling the team and discussing roles and responsibilities of each member on the team.
D . Assembling the team and asking the members to achieve a milestone in a small iteration.

Answer: C

Leave a Reply

Your email address will not be published.