What should the project team do next?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

A product’s scope and acceptance criteria have been defined, and the product is planned for release at the end of the next quarter.

What should the project team do next?
A . Estimate the project team’s capacity.
B . Determine how much work can be delivered.
C . Calculate how much work will fit into the next iteration.
D . Estimate items in the product backlog.

Answer: A