An agile team is preparing a release plan for a project.

What information will the team need to complete this plan?
A . Amount of work needed to complete a single user story
B . Amount of work that can be accomplished by each team member
C . Amount of work that can be accomplished in an iteration
D . Amount of work that can be accomplished by the entire team

Answer: C