Based on the chart, what is the current status of the iteration when comparing story points planned versus completed?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

Based on the chart, what is the current status of the iteration when comparing story points planned versus completed?

A . The iteration is in jeopardy.
B . The team has removed scope.
C . The iteration is ahead of schedule.
D . The team’s velocity is constant.

Answer: C