What should the agile practitioner do?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

An agile team provides feedback that user stories include insufficient details to understand the requirements.

What should the agile practitioner do?
A . Coach the product owner to update only the acceptance criteria.
B . Instruct the agile team to fix the user stories during the next retrospective.
C . Facilitate a user story workshop with the agile team.
D . Inform the product owner’s manager that the work items provide insufficient detail.

Answer: B