A project sponsor approaches the project manager with a change request. During the conversation, the project sponsor claims to understand the impact of the change to the project length and has the budget to handle the cost. The sponsor also tells the project manager to send whatever needs a signature.

Posted by: Pdfprep Category: PK0-004 Tags: , ,

A project sponsor approaches the project manager with a change request. During the conversation, the project sponsor claims to understand the impact of the change to the project length and has the budget to handle the cost. The sponsor also tells the project manager to send whatever needs a signature.

The project manager’s NEXT step should be to:
A . document the change
B . implement the change
C . communicate the change
D . prioritize the change

Answer: A

Leave a Reply

Your email address will not be published.