The client accepts the critical design review.

Which of the following meetings should be held to move to the NEXT step in the project?
A . Execution
B . Kickoff
C . Closure
D . Planning

Answer: B

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 112