Which of the following actions should the project manager take?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project.

Which of the following actions should the project manager take?
A . Alert the project sponsor of the situation.
B . Contact the customer and request more funding.
C . Announce the project will end early due to lack of funds.
D . Attempt to save money in downstream activities.

Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 233