Which of the following is the BEST way for the PM to provide this information?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

A PM is asked to keep the Chief Information Officer (CIO) informed of a project’s health at a high level on a daily basis.

Which of the following is the BEST way for the PM to provide this information?
A . Status report
B . Meeting minutes
C . Dashboard
D . Email

Answer: D