During which of the following project phases is this determination MOST likely to happen?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

A project manager determines deliverables are not meeting customer specifications.

During which of the following project phases is this determination MOST likely to happen?
A . Monitor and control
B . Execution
C . Closing
D . Planning

Answer: A