The PMO is responsible for: (Choose two.)

Posted by: Pdfprep Category: PK0-004 Tags: , ,

The PMO is responsible for: (Choose two.)
A . managing the project plan, scope, risk, and budget.
B . contributing expertise, deliverables, and estimates of costs.
C . setting standards and practices for the organization and providing governance.
D . outlining consequences of non-performance and coordinating between disparate projects.
E . approving funding, developing the project schedule, and gathering high-level requirements.

Answer: CD

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 85