In which of the following documents can this information be found?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

A project manager needs to identify the resources assigned to a particular task.

In which of the following documents can this information be found?
A . Project schedule
B . Cost plan
C . Scope statement
D . Impact assessment

Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 156