Which of the following describes why the team was asked to inspect and review missing parts, poor adhesives, and faulty installation?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

A project manager creates a Pareto chart based on the table below:

Which of the following describes why the team was asked to inspect and review missing parts, poor adhesives, and faulty installation?
A . To take preventive action and identify the causes resulting in the highest number of issues
B . To take corrective action and identify the effects resulting in the highest number of issues
C . To take preventive action and identify and frequencies resulting in the highest number of issues
D . To take corrective action and identify the causes resulting in the highest number of issues

Answer: A