A project manager is justifying a required change with the associated impact on the project.

Which of the following is the NEXT step?
A . Implementation
B . Approval
C . Validation
D . Auditing

Answer: B

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294