Which of the following should the project manager bring to the meeting to support this recommendation?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.

Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)
A . The issue log to show why the vendor should be replaced.
B . The team action items to show why the vendor should be replaced.
C . The scope statement to show why the vendor should be replaced.
D . A procurement plan to show why the vendor should be replaced.
E . A change management plan to have the vendor replaced.

Answer: AE

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 291,

p. 327

Leave a Reply

Your email address will not be published.