A PM notes a feature that was delivered does not appear in the latest requirement document. The PM immediately submits a change request for remediation.

Which of the following actions has the PM omitted?
A . Identifying the risk
B . Obtaining approval from the CCB
C . Evaluating the impact of the risk
D . Communicating to stakeholders

Answer: B