Which of the following documents should the project coordinator use?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies.

Which of the following documents should the project coordinator use?
A . Risk register
B . Issue log
C . Communication plan
D . Status report

Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 240