According to the communication management plan, the project scheduler is required to post weekly status reports on the project’s intranet site.

Posted by: Pdfprep Category: PK0-004 Tags: , ,

According to the communication management plan, the project scheduler is required to post weekly status reports on the project’s intranet site.

From the stakeholders’ point of view, accessing the weekly report is an example of:
A . interorganizational preferences
B . personal preferences
C . the interactive method
D . the pull method

Answer: D