Which of the following should be the project manager’s NEXT steps?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

A vendor is unable to deliver an order by the specified date.

Which of the following should be the project manager’s NEXT steps? (Choose two.)
A . The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.
B . The project manager should notify the project sponsor to update the schedule in the documentation because the project could potentially encounter delays.
C . The project manager should adjust the schedule in the documentation and, if necessary, take steps to rush other areas of the schedule so the project will not encounter delays.
D . The project manager should update the project management plan in the documentation to reflect the reason for the possible delay in the project timeline.
E . The project manager should update the procurement plan and action items to reflect the possible delay in the project timeline.

Answer: AD