Which of the following documents should be used to provide high-level reporting to key stakeholders?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

Which of the following documents should be used to provide high-level reporting to key stakeholders?
A . Dashboard
B . Communication plan
C . Statement of work
D . Project charter

Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 325