Which of the following project phases is the project team moving between?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

The project team is moving from high-level risks to detailed risks.

Which of the following project phases is the project team moving between?
A . Execution to monitor and control
B . Initiation to planning
C . Initiation to monitor and control
D . Planning to execution

Answer: D