Posted by: Pdfprep Category: PK0-004 Tags: PK0-004 exam questions, PK0-004 practice exam, CompTIA Project+ Post Date: November 7, 2020 Pdfprep2020-11-07T01:27:15+00:00 Which of the following is the first document issued during the procurement process in a project?A . POB . RFPC . RFID . RFQ View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.