Which of the following change control processes is being mismanaged?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

A project manager is assigned to a project that was previously managed by a peer project manager. The project manager identifies several modifications that were deployed prior to CCB approval.

Which of the following change control processes is being mismanaged?
A . Change validation with quality checks
B . Regression planning
C . Identify approval authority
D . Change implementation

Answer: D