Which of the following represents the critical path?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day.

Which of the following represents the critical path?
A . Five days
B . Six days
C . Seven days
D . Eight days

Answer: B