Which of the following will identify the MOST potential project risks?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

Which of the following will identify the MOST potential project risks?
A . Cost-benefit analysis
B . Past project documentation
C . Project budget
D . Benchmarking

Answer: B