Which of the following activities would have allowed the project manager to identify and correct this issue in advance?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week.

Which of the following activities would have allowed the project manager to identify and correct this issue in advance?
A . Risk identification
B . Gate review
C . Resource allocation
D . Resource leveling

Answer: C

Leave a Reply

Your email address will not be published.