Which of the following should a project manager consider as part of a make or buy analysis?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

Which of the following should a project manager consider as part of a make or buy analysis?
A . Organization type
B . KPIs
C . Project charter
D . Trade secrets

Answer: B

Leave a Reply

Your email address will not be published.