The Controlling a Stage process is used for which of the following?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

The Controlling a Stage process is used for which of the following?
A . Day-to-day management of each management stage of a project
B . Closure of the project prematurely or at the project’s natural end
C . Creation and quality control of the specialist products
D . Preparing a Stage Plan near the end of each stage

Answer: A