Which statement describes risk cause?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which statement describes risk cause?
A . The impact of a risk on the stage and project tolerance
B . The situation or event that gave rise to a risk
C . The area of uncertainty in terms of the threat or opportunity
D . How likely a risk is to occur in a given project situation

Answer: B