The outputs from a PRINCE2 project are considered to be what?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

The outputs from a PRINCE2 project are considered to be what?
A . The business benefits
B . Any of its tangible or intangible specialist products
C . Its Resources
D . The results of change

Answer: B