Which product does the Project Board use as a base against which to monitor project progress on a stage by stage basis?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which product does the Project Board use as a base against which to monitor project progress on a stage by stage basis?
A . Stage Plan
B . Project Plan
C . Programme Plan
D . Benefits Review Plan

Answer: B