The Project Board have overall control at what level?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

The Project Board have overall control at what level?
A . Day-to-day control for a management stage within stage tolerance
B . Work Package level within Work Package tolerance
C . Project level within project tolerance
D . All levels of plans and tolerances

Answer: C