Which product would the Project Manager use for gathering Work Package progress information?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which product would the Project Manager use for gathering Work Package progress information?
A . Highlight Report
B . Daily Log
C . Checkpoint Report
D . Product Status Account

Answer: C