Posted by: Pdfprep Category: PRINCE2 Tags: Polycom Certification, PRINCE2 exam questions, PRINCE2 practice exam Post Date: November 23, 2020 Pdfprep2020-11-23T16:31:59+00:00 Which product would the Project Manager use for gathering Work Package progress information?A . Highlight ReportB . Daily LogC . Checkpoint ReportD . Product Status Account View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.