In which process would a concern about the amount of stage tolerance remaining be recorded in the Issue Register?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

In which process would a concern about the amount of stage tolerance remaining be recorded in the Issue Register?
A . Directing a Project
B . Managing a Stage Boundary
C . Managing Product Delivery
D . Controlling a Stage

Answer: D