Which of the following would NOT be classified as a threat to a project?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which of the following would NOT be classified as a threat to a project?
A . A competitor may launch a rival product first thus affecting the expected market share for the product
B . It is possible that the product completes user acceptance testing in a single test cycle rather that the scheduled two
C . A prototype may be damaged in transit
D . A critical meeting could be affected by air travel disruption

Answer: B