In which situation might the Controlling a Stage process be used?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

In which situation might the Controlling a Stage process be used?
A . Managing a long initiation stage of a complex project
B . Managing the activities of a complex programme
C . Managing support activities following the handover of the products to the operational environment
D . Creating an Exception Plan to replace the current Stage Plan

Answer: A