Which process controls the link between the Project Manager and the Team Manager(s)?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which process controls the link between the Project Manager and the Team Manager(s)?
A . Controlling a Stage
B . Managing a Stage Boundary
C . Managing Product Delivery
D . Directing a Project

Answer: C