Which product would contain information on project and stage tolerance status, products completed during the period and a summary of actual or potential problems and risks?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which product would contain information on project and stage tolerance status, products completed during the period and a summary of actual or potential problems and risks?
A . Product Status Account
B . Communication Management Strategy
C . Highlight Report
D . Risk Register

Answer: C