Posted by: Pdfprep
Post Date: October 17, 2020
Which of the following would be carried out as part of a post-project benefits review?
A . An assessment of whether the project fulfilled its original objectives
B . A review of the performance of the project’s products in operational use and identification of whether there have been any side-effects
C . An assessment of the project’s risk management procedure
D . A review of the performance of the project management method and the project management team
Answer: B
Leave a Reply