Which of the following would be carried out as part of a post-project benefits review?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which of the following would be carried out as part of a post-project benefits review?
A . An assessment of whether the project fulfilled its original objectives
B . A review of the performance of the project’s products in operational use and identification of whether there have been any side-effects
C . An assessment of the project’s risk management procedure
D . A review of the performance of the project management method and the project management team

Answer: B

Leave a Reply

Your email address will not be published.