According to PRINCE2, which of the following statements is FALSE regarding project closure?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

According to PRINCE2, which of the following statements is FALSE regarding project closure?
A . A clear end to the project gives recognition that the original objectives have been met
B . A clear end to the project provides an opportunity to ensure that all unachieved goals and objectives are identified
C . A clear end to the project enables the organization to understand the work that needs to be done to deliver the project’s products
D . A clear end to the project transfers ownership of the products to the customer

Answer: C