The remediation plan should be evaluated at what point in the change lifecycle?

Posted by: Pdfprep Category: ITIL Tags: , ,

The remediation plan should be evaluated at what point in the change lifecycle?
A . Before the change is approved
B . Immediately after the change has failed and needs to be backed out
C . After implementation but before the post implementation review
D . After the post implementation review has identified a problem with the change

Answer: A