Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
A .  Procurement documents
B .  Communications plan
C .  Project charter
D .  Stakeholder register

Answer: C