Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
A .  Bottom-up
B .  Parametric
C .  Analogous
D .  Three-point

Answer: C